Contract No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work (Stage
2) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a
and FEP-07/364/2009/A Monthly Environmental Monitoring
& Audit Report
- february 2012 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
                         Raymond Dai Environmental Team
Leader |
|
DATE: |
|
9 March 2012 |
1.1    Scope
of the Report
1.2    Structure
of the Report
2.   Project Background
2.1    Background
2.2    Scope
of the Project and Site Description
2.3    Division
of the Project Responsibility
2.4    Project
Organization and Contact Personnel
3.   status of regulatory compliance
3.1    Status
of Environmental Licensing and Permitting under the Project
4.   Monitoring
Requirements
4.1    Noise
Monitoring
4.2    Air
Monitoring
5.   Monitoring Results
5.1    Noise
Monitoring Results
5.2    Real Time Noise Monitoring Results
5.3    Air
Monitoring Results
5.4    Waste
Monitoring Results
6.1    Noise
Monitoring
6.2    Real Time Noise Monitoring
6.3    Air
Monitoring
6.4    Review
of the Reasons for and the Implications of Non-compliance
6.5    Summary
of action taken in the event of and follow-up on non-compliance
7.   Cumulative Construction Impact due to the
Concurrent Projects
8.   Environmental Site
Audit
9.   Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1    Schedule
2 Designated Projects under this Project
Table 2.2   Details of Individual Contracts under the Project
Table 2.3   Contact Details of Key Personnel
Table 3.3   Summary of submission status under FEP-03/364/2009
Table 3.5   Summary of submission status under FEP-02/364/2009
Table 3.7   Summary of submission status under FEP-01/364/2009
Table 3.9   Summary of submission status under FEP-05/364/2009/A
Table 3.10  Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/15
Table 3.11  Summary of submission status under FEP-06/364/2009/A
Table 3.12  Cumulative Summary of Valid Licences and Permits under Contract no.
HY/2009/19
Table 3.13  Summary of submission status under FEP-07/364/2009/A
Table 4.1   Noise Monitoring Stations
Table 4.2   Real Time Noise Monitoring Stations
Table 4.3   Air Monitoring Stations
Table 5.1    Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.2    Noise Monitoring Stations for Contract no. HY/2009/18
Table 5.3    Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Table 5.4    Noise Monitoring Stations for Contract no. HY/2009/15
Table 5.5    Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.6   Real Time Noise Monitoring Stations for Contract no. HY/2009/17
Table 5.7   Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8    Air Monitoring Station for Contract no. HY/2009/17
Table 5.9    Air Monitoring Stations for Contract no. HY/2009/18
Table 5.10   Air Monitoring Station for Contract no. HK/2009/01
Table 5.11   Air Monitoring Station for Contract no. HK/2009/02
Table 5.12   Air Monitoring Station for Contract no. HY/2009/15
Table 5.13   Air Monitoring Stations for Contract no. HY/2009/19
Table 5.14  Details of Waste Disposal for Contract no. HY/2009/17
Table 5.15  Details of Waste Disposal for Contract no. HK/2009/01
Table 5.16  Details of Waste Disposal for Contract no. HK/2009/02
Table 5.17  Details of Waste Disposal for Contract no. HY/2009/18
Table 5.18  Details of Waste Disposal for Contract no. HY/2009/15
Table 5.19  Details of Waste Disposal for Contract no. HY/2009/19
Table 8.1   Summary of Environmental Inspections for Contract no. HY/2009/15
Table 8.2   Summary of Environmental Inspections for Contract no. HY/2009/18
Table 8.3   Summary of Environmental Inspections for Contract no. HY/2009/19
Table 8.4   Summary of Environmental Inspections for Contract no. HK/2009/01
Table 8.5   Summary of Environmental Inspections for Contract no. HK/2009/02
Table 9.1   Cumulative Statistics on Complaints
Table 9.2   Cumulative Statistics on Successful Prosecutions
lIST OF
FIGUREs
Figure
2.1       Project
Layout
Figure
2.2       Project Organization Chart
Figure 4.1        Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1     Environmental
Mitigation Implementation Schedule
Appendix 4.1     Action and
Limit Level
Appendix
4.2     Copies of Calibration
Certificates
Appendix
5.1     Monitoring Schedule for Reporting
Month and Coming month
Appendix 5.2     Noise Monitoring Results and Graphical
Presentations
Appendix 5.3     Air Quality Monitoring Results and Graphical
Presentations
Appendix
5.4     Real-time Noise Monitoring Results and Graphical
Presentations
Appendix 6.1     Event
Action Plans
Appendix
6.2     Notification
of Exceedance
Appendix
9.1     Complaint Log
Appendix 10.1   Construction
Programme of Individual Contracts
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot
- Advanced piling works under FEP-03/364/2009
 -
ELS works
for basement construction for pile cap construction.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under
FEP-05/364/2009/A
 -
Instrumentation works for Manholes and Intake Culvert Survey
 -
Excavation of trial pit
 -
Drainage work
 -
Site investigation and pre-drilling works
 -
Diaphragm wall construction
 -
Hoarding erection
 -
Roadwork
 -
Grout curtain
 -
Sheet-piling
 -
Tree pruning
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009
 -
Diaphragm wall construction works for CWB (stage 1) and SCL protection
Works
 -
Diaphragm wall construction works for CWB (stage2)
 -
Pre-drill works for CWB (stage 2).
 -
Pre-bored H pilling works for CWB (stage 1)
 -
Pre-bored H pilling for exhaust duct
 -
Installation of shoring system for construction of CWB Diaphragm wall
(stage 1)
 -
Installation of shoring system for construction of exhaust duct
structure at stage 1
 -
Pre-treatment works for construction of CWB Diaphragm wall (stage 2)
 -
Guide wall construction for construction of CWB Diaphragm wall (stage 2)
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
 -
Shear pin
and Pumping test at WCR1 area.
Contract
no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
 -
Diaphragm
wall construction preparation works at TS4
 -
ELS works
at TS1 and TPCWAE
 -
Night
time protection works at CHT
 -
Cut off
wall preparation works at Hung Hing Road and POC
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under
FEP-07/364/2009/A
 -
Preparation
works and concreting of marine piles
 -
Fabrication
of bored piling platform
 -
Bored
piling (Land)
 -
Ground
contamination assessment
 -
D-wall Construction
(North & South Section)
 -
Guide
wall construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Marine
Piling
 -
Preparing
for fabrication of temporary steel bridge for Culvert U
 -
Construction
of Jetty
Noise Monitoring
iii. ix.Monitoring
for report of review baseline noise level was performed from 11 April 2011 to 8
June 2011. Then the report was submitted
on the 20 June 2011, verified by IEC on 18 July 2011 and was approved by ER by
January 2012. The new baseline is used
for the noise calculation of this reporting month starting from January 2012.
iv.iii.
Noise monitoring
during daytime was conducted at M1a - Harbour Road Sports Center; M2b -
Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b -
City Garden, M6 - HK Baptist Church Henrietta Secondary School,
M7e and M7w  International Finance Centre Eastern and Western End
of Podium on a weekly basis.  /span>No action or limit level exceedance was
recorded during the reporting month.
v. iv.
24-hour real
time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section
Whitefield Depot for the pilling works in FEHD Whitfield Depot and RTN2  
Tunnel (North Point Section) and Island Eastern Corridor Link. No project
related action and limit level exceedance was recorded in the
reporting period.
Air Monitoring
vi. v.
Due
to lack of electricity supply, the 24 TSP monitoring at the following stations
were rescheduled
CMA1b: from 13 Feb 2012 to 16 Feb 2012
CMA3a: from 13 Feb 2012 to 14 Feb 2012
CMA5a:
from 18 Feb 2012 to 20 Feb 2012
vii.vi.
1-hour and
24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b -
Oil Street Community Liaison Centre; CMA2a - Causeway Bay Community Center;
CMA3a - CWB PRE Site Office Area; CMA4a  Society for the Prevention of Cruelty
to Animals; CMA5a -
Children Garden opposite to Pedestrian Plaza; MA1e and
MA1w  International Finance Centre eastern and western wing on every six days basis. No action and limit
level exceedance were recorded in the reporting period.
Complaints, Notifications of Summons and Successful
Prosecutions
viii.vii.
There
was no environmental complaint in this reporting month.
Site Inspections and Audit
ix.viii.
The Environmental Team (ET) conducted weekly site inspections for
Contract no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01 and HK/2009/02
in this reporting period. The Contractors rectified major observations and
recommendations made during the audit sessions. No non-conformance was
identified during the site inspections.
x.ix.
In coming reporting month, the principal work activities of individual
contracts are anticipated as follows:
Contract no. HY/2009/17  
Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works
under FEP-03/364/2009
 -
ELS works
for basement construction for pile cap construction.
Contract no. HY/2009/18  Central  Wan Chai
Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
 -
Instrumentation works for Manholes and Intake Culvert Survey
 -
Excavation of trial pit
 -
Drainage work
 -
Site investigation and pre-drilling works
 -
Diaphragm wall construction
 -
Hoarding erection
 -
Roadwork
 -
Grout curtain
 -
Sheet-piling
 -
Tree pruning
Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under
FEP-02/364/2009
 -
Diaphragm wall construction works for both CWB and SCL Protection Works
 -
Guide wall for construction of CWB Diaphragm wall at Stage 2
 -
Pilling works for CWB and exhaust duct at Stage 1
 -
Pilling works for SCL Protection Works
 -
Installation of sheet pile for construction of exhaust duct
 -
Excavation woks
 -
Installation
of sheet pile for construction exhaust duct
 -
Installation
of sheet pile for construction of SCL top slab
Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
 -
Deep excavation works below
-0.9mPD for western tunnel portion and below +1.5mPD for eastern tunnel
portion.
 -
Shear pin
and Pumping test at WCR1 area.
Contract
no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
 -
Diaphragm wall construction at
TS4
 -
ELS works at TS1 and TPCWAE
 -
Night time protection works at
CHT
 -
Cut off wall preparation works at
Hung Hing Road and POC
Contract
no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
 -
Road
works at Watson Road
 -
Fabrication
of bored piling platform
 -
Bored
piling (Land)
 -
Ground
contamination assessment
 -
Pre-drilling
works for bored pile and Diaphragm wall
 -
D-wall Construction
(North & South Section)
 -
Guide
wall construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Marine
Piling
 -
Installation
of temporary steel bridge at Culvert U
1.1.1.
Lam Geotechnics
Limited (LGL) has been appointed to work as the Environmental Team (ET) under
Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report
presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A
Manual and  /span>Environmental Monitoring and Audit Requirements /span> under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A, Further Environmental
Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009,
FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A during the period
28th January 2012 to 27th
February 2012. The cut-off date of reporting is at 27th of each reporting
month.
Section
1     Introduction
 details the scope and structure of the report.
Section
2     Project Background
 summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section
3     Status of Regulatory
Compliance  summarizes the status of valid
Environmental Permits / Licenses during the reporting period.
Section
4     Monitoring Requirements
 summarizes all monitoring parameters, monitoring methodology and equipment,
monitoring locations, monitoring frequency, criteria and respective event and
action plan and monitoring programmes.
Section
5     Monitoring Results
 summarizes the monitoring results obtained in the reporting period.
Section
6     Compliance Audit
 summarizes the auditing
of monitoring results, all exceedances environmental parameters.
Section
7     Cumulative Construction
Impact due to the Concurrent Projects  
summarizes the relevant
cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section
8     Site Inspection  
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9     Complaints, Notification of
summons and Prosecution  summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10    Conclusion
2.1.1.
“Wan Chai
Development phase II and Central-Wan Chai Bypass and “Central-Wan Chai Bypass
and Island Eastern Corridor Link (hereafter called “the Project  are Designed
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved
on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose
of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North
and North Point for construction of the Central-Wan Chai Bypass and Island
Eastern Corridor Link (CWB). Land formed under the project will be developed as
a world-class waterfront promenade joining that at the new Central waterfront
for public enjoyment.
2.1.3.
There is a
compelling and present need for the CWB to provide relief to the very congested
east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the
Corridor) which is currently operating beyond its capacity. The CWB will
provide relief to the existing congestion along the Corridor and cater for the
anticipated growth of traffic on Hong Kong Island. Without the CWB and its
access roads, there will not be sufficient capacity to serve the heavy traffic
demands at both strategic and local levels.
2.2.1.
Design and Construction of Central  Wan Chai Bypass and Island Eastern
Corridor Link under the Project involves the construction and operation of a
trunk road and its road tunnel more than 800m in length between portals that is
shown at Figure 2.1.
2.2.2.
The study area encompasses existing
developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
 -
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
 -
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
 -
Tunnel
control buildings and ventilation buildings;
 -
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
Causeway Bay area;
 -
Associated
road lighting, road signing, traffic control and surveillance system; and
 -
Other
associated works.
2.2.3.
The project also
contains various Schedule 2 DPs that, under the EIAO, require Environmental
Permits (Eps) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the
five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1   Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads |
Schedule
2, Part I, A.1 and A.7 |
Trunk
road and road tunnel more than 800 m in length |
DP2 |
Road P2
and other roads which are classified as primary/district distributor roads |
Schedule
2, Part I, A.1 |
Primary
/ district distributor roads |
DP3 |
Reclamation
works including associated dredging works |
Schedule
2, Part I, C.1 and C.12 |
Reclamation
more than 5 ha in size and a dredging operation less than 100 m from a
seawater intake point |
DP5 |
Wan Chai
East Sewage Outfall |
Schedule
2, Part I, F.5 and F.6 |
Submarine
sewage pipelines with a total diameter more than 1,200 mm and include a
submarine sewage outfall |
DP6 |
Dredging
for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui |
Schedule
2, Part I, C.12 |
A dredging
operation less than 100 m from a seawater intake point |
2.3.1.
Due to the
multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be commenced. Contractors of individual contracts will be
required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided
accordingly to facilitate the implementation of EM&A programme and to
streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2.
In the reporting
month, Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section)
was commenced on 13 July 2011. The details of individual contracts are summarized in Table2.2.
Table 2.2  Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central
 Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central
 Wan Chai Bypass (CWB)  Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai
Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre  Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai
Development Phase II  Central  Wan Chai Bypass at Wan Chai East(CWB Tunnel)
|
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai
Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1 |
13 July 2011 |
HY/2009/19 |
Central
 Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor
Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and Highways Department are
the overall project controllers for the Wan Chai Development Phase II and
Central-Wan Chai Bypass respectively. For the construction phase of the
Project, Project Engineer, Contractor(s), Environmental Team and Independent
Environmental Checker are appointed to manage and control environmental issues.
2.4.2.
The proposed
project organization and lines of communication with respect to environmental
protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer
for WDII |
Principal
Resident Engineer |
Mr.
Frankie Fan |
2587
1778 |
2587 1877 |
Engineer
for CWB |
Principal
Resident Engineer |
Mr.
Peter Poon |
3916
1818 |
3529 2829 |
|
Lam Woo &
CO., LTD. |
Contractor
under Contract no. HY/2009/17 |
Project
Manager |
Mr. K.
S. Law |
9090
1378 |
2566 7522 |
Site
Agent |
Mr. Tony
Au |
9725
5874 |
2566 7522 |
||
Sub Agent |
Mr.
Johnny Wong |
9725
5870 |
2566 7522 |
||
Chun Wo  
Leader Joint Venture |
Contractor
under Contract no. HK/2009/01 |
Joint
Venture Board Representative |
Mr. PL
Yue |
2162
9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub
Agent |
Mr.
Terry Wong |
9757
9846 |
|||
Construction Manager |
Mr. Wyman Wong |
9627
2467 |
|||
Construction Manager |
Mr. Jack Chu |
9775
2467 |
|||
Construction Manager |
Mr KK Yuen |
9498
1213 |
|||
Construction Manager |
Mr. Andy
Yu |
9648
4896 |
|||
Environmental Officer (Compliance
Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental Supervisor |
Ms. Kiwi Chan |
6227 8840 |
|||
|
|
Environmental Supervisor |
Mr.
Yeung Sze King |
9047
9952 |
|
Environmental Supervisor |
Mr. Les
Chow |
6692
2423 |
|
||
Environmental Supervisor |
Mr. Otto
Yau |
9260
4485 |
|
||
Chun Wo
 CRGL Joint Venture |
Contractor
under Contract no. HK/2009/02 |
Project
Manager |
Mr. Chan
Sing Cho |
3658-3002 |
2827 9996 |
Site
Agent |
Mr. Mak
Kam Wing |
3658-3044 |
|||
Quality
& Environmental Manager |
Mr. C.P.
Ho |
3658-3000 |
|||
Environmental
Officer |
Ms Flora
Ng |
3658-3064 |
|||
Chun Wo
- CRGL - MBEC Joint Venture |
Contractor
under Contract no. HY/2009/19 |
Project
Manager |
Mr.
Rayland Lee |
3758 8879 |
2570 8013 |
Site
Agent |
Mr.
Cheung Kit Cheung |
6909
1555 |
|||
Environmental
Engineer |
Mr.
Simon Wong |
9281
4346 |
|||
Environmental
Manager / Environmental
Officer |
Mr. M.H.
Isa |
9884
0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Leighton
Contractors (Asia) Limited |
Contractor
under Contract no. HY/2009/18 |
Site
Agent |
Mr.
Brian Gillon |
2214 7700 |
|
Deputy
Site Agent |
Mr.
Desmond Sze |
2214 7703 |
|||
Environmental
Officer |
Mr.
Anfernee Chow |
2214 7721 |
|||
Environmental
Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental
Supervisor |
Ryan
Tsui |
2214 7705 |
|||
China
State Construction Engineering (HK) Ltd. |
Contractor
under Contract no. HY/2009/15 |
Project
Manager |
Mr. M Y
Wong |
2823
7879 |
2566 2192 |
Site
Agent |
Mr. P J
Fan |
3557
6368 |
|||
Contractor’s
Representative |
David Lau |
3557 6358 |
|||
Head of
construction |
Mr. Roger
Cheung |
3557
6371 |
|||
Environmental
Officer |
Mr. Daniel
Sin |
3557
6215 |
|||
Environmental
Supervisor |
Mr. Kelven
Yip |
3557
6347 |
|||
Environmental
Supervisor |
Mr. Tim
Fung |
3557
6349 |
|||
ENVIRON
Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr.
David Yeung |
3743
0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work activities of individual
contracts are included as follows:
Contract no. HY/2009/17  
Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works
under FEP-03/364/2009
 -
ELS works
for basement construction for pile cap construction.
Contract
no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
 -
Instrumentation works for Manholes and Intake Culvert Survey
 -
Excavation of trial pit
 -
Drainage work
 -
Site investigation and pre-drilling works
 -
Diaphragm wall construction
 -
Hoarding erection
 -
Roadwork
 -
Grout curtain
 -
Sheet-piling
 -
Tree pruning
Contract no. HK/2009/01  Wan Chai
Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre  Tunnel Works under FEP-02/364/2009
 -
Diaphragm wall construction works for CWB (stage 1) and SCL protection
Works
 -
Diaphragm wall construction works for CWB (stage2)
 -
Pre-drill works for CWB (stage 2)
 -
Pre-bored H pilling works for CWB (stage 1)
 -
Pre-bored H pilling for exhaust duct
 -
Installation of shoring system for construction of CWB Diaphragm wall
(stage 1)
 -
Installation of shoring system for construction of exhaust duct
structure at stage 1
 -
Pre-treatment works for construction of CWB Diaphragm wall (stage 2)
 -
Guide wall construction for construction of CWB Diaphragm wall (stage 2)
Contract no. HK/2009/02  Wan Chai
Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
 -
Shear pin
and Pumping test at WCR1 area.
Contract no. HY/2009/15  
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
 -
Diaphragm
wall construction preparation works at TS4
 -
ELS works
at TS1 and TPCWAE
 -
Night
time protection works at CHT
 -
Cut off
wall preparation works at Hung Hing Road and POC
Contract no. HY/2009/19  Central
 Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
 -
Preparation
works and concreting of marine piles
 -
Fabrication
of bored piling platform
 -
Bored
piling (Land)
 -
Ground
contamination assessment
 -
D-wall Construction
(North & South Section)
 -
Guide wall
construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Marine
Piling
 -
Preparing
for fabrication of temporary steel bridge for Culvert U
 -
Construction
of Jetty
2.4.4.
In coming
reporting month, the principal work activities of individual contracts are
anticipated as follows:
Contract no. HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD
Whitfield Depot  Advanced piling works under FEP-03/364/2009
 -
ELS works
for basement construction for pile cap construction.
Contract no. HY/2009/18  Central  Wan Chai
Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
 -
Instrumentation works for Manholes and Intake Culvert Survey
 -
Excavation of trial pit
 -
Drainage work
 -
Site investigation and pre-drilling works
 -
Diaphragm wall construction
 -
Hoarding erection
 -
Roadwork
 -
Grout curtain
 -
Sheet-piling
 -
Tree pruning
Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under
FEP-02/364/2009
 -
Diaphragm wall construction works for both CWB and SCL Protection Works
 -
Guide wall for construction of CWB Diaphragm wall at Stage 2
 -
Pilling works for CWB and exhaust duct at Stage 1
 -
Pilling works for SCL Protection Works
 -
Installation of sheet pile for construction of exhaust duct
 -
Excavation woks
 -
Installation
of sheet pile for construction exhaust duct
 -
Installation
of sheet pile for construction of SCL top slab
Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
 -
Deep excavation works below
-0.9mPD for western tunnel portion and below +1.5mPD for eastern tunnel
portion.
 -
Shear pin
and Pumping test at WCR1 area.
Contract
no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
 -
Diaphragm
wall construction at TS4
 -
ELS works
at TS1 and TPCWAE
 -
Night
time protection works at CHT
 -
Cut off
wall preparation works at Hung Hing Road and POC
Contract
no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
 -
Road
works at Watson Road
 -
Fabrication
of bored piling platform
 -
Bored
piling (Land)
 -
Ground
contamination assessment
 -
Pre-drilling
works for bored pile and Diaphragm wall
 -
D-wall Construction
(North & South Section)
 -
Guide
wall construction for D-wall / Barette at North side
 -
Construction
works for Box Culvert T
 -
Marine
Piling
 -
Installation
of temporary steel bridge at Culvert U
3.1.1.
A summary of the
current status on licences and/or permits on environmental protection pertinent
to the Project is shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
 4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Valid |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Valid |
3.1.2.
Due to the
multi-contract nature of the Project, the status of permits and/or licences
under the individual contract(s) are presented as below:
Contract no. HY/2009/17  Central
 Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under
FEP-03/364/2009
3.1.3.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table
3.2 and Table 3.3.
Table
3.2  Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
N/A |
Valid |
Notification of Works Under APCO |
319348 |
13 Jul 2010 |
N/A |
Valid |
Discharge Licence |
WT00007212-2010 |
5 Aug 2010 |
5 Aug 2010  31 Aug 2015 |
Valid |
Registration as a Waste Producer |
5213-151-L2608-05 |
13 July 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7010400 |
16 Mar 2010 |
N/A |
Valid |
Table 3.3  Summary
of submission status under FEP-03/364/2009
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization
of Main Construction Companies |
18 September 2010 |
Conditions 2.7 and 2.8 |
Submission of works
schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management Plan |
1 September 2010 |
Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus
near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.4.
The construction works was completed, and the FEP was surrendered by the
Contractor on 11 February 2011.
Contract no.
HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009
3.1.5.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5
Table 3.4  Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0832-11 |
7 Sep 2011 |
03 Sep 2011 to 02 Mar 2012 |
Cancelled |
|
GW-RS0850-11 |
12 Sept 2011 |
14 Sept 2011 to 13 Mar 2012 |
Valid |
|
GW-RS0851-11 |
12 Sept 2011 |
16 Sept 2011 to 15 Mar 2012 |
Valid |
|
GW-RE0716-11 |
28 Sept 2011 |
07 Oct 2011 to 29 Mar 2012 |
Valid |
|
GW-RS1031-11 |
02 Nov 2011 |
07 Nov 2011 to 05
May 2012 |
Valid |
|
GW-RS1094-11 |
23 Nov 2011 |
27 Nov 2011 to 26
May 2012 |
Valid |
|
GW-RS1227-11 |
30 Dec
2011 |
30 Dec
2011 to 26 Jul 2012 |
Valid |
|
GW-RS0038-12 |
16 Jan
2012 |
15 Jan
2012 to 12 Jul 2012 |
Valid |
|
GW-RS0158-12 |
24 Feb
2012 |
24 Feb
2012 to 23 Aug 2012 |
Valid |
|
GW-RS0181-12 |
24 Feb
2012 |
27 Feb
2012 to 23 Aug 2012 |
Valid |
|
GW-RS0213-12 |
28 Feb
2012 |
29 Feb
2012 to 27 Aug 2012 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar
2015 |
Valid |
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing account
under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan
2010 |
N/A |
Valid |
Table 3.5  Summary
of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May
2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
18 May 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
25 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
10 Jun 2011 |
Contract no.
HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai
East (CWB Tunnel) under FEP-01/364/2009
3.1.6.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.
Table 3.6  Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction
Noise Permit (CNP) for non-piling equipment |
GW-RS0649-11 |
22 July 2011 |
1 Aug 2011 to 31 Jan 2012 |
Expired |
|
GW-RE0710-11 |
30 Sept
2011 |
1 Nov
2011 to 30 Apr 2012 |
Valid |
|
GW-RS0716-11 |
2 Aug 2011 |
12 Aug 2011 to 11 Feb 2012 |
Cancelled |
|
GW-RS0833-11 |
8 Sept
2011 |
10 Sept
2011 to 4 Mar 2012 |
Cancelled |
|
GW-RS0918-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0929-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Cancelled |
|
GW-RS0930-11 |
11 Oct
2011 |
1 Nov
2011 to 30 Apr 2012 |
Valid |
|
GW-RS0931-11 |
7 Oct
2011 |
10 Oct
2011 to 9 Apr 2012 |
Valid |
|
GW-RS0941-11 |
20 Oct
2011 |
23 Nov
2011 to 22 May 2012 |
Valid |
|
GW-RS0955-11 |
14 Oct
2011 |
23 Nov
2011 to 22 May 2012 |
Valid |
|
GW-RS0968-11 |
20 Oct
2011 |
18 Nov
2011 to 17 May 2012 |
Valid |
|
GW-RS0983-11 |
24 Oct
2011 |
26 Oct
2011 to 23 April 2012 |
Cancelled |
|
GW-RS0984-11 |
 /span>25 Oct 2011 |
30 Oct
2011 to 27 April 2012 |
Valid |
|
GW-RS1028-11 |
3 Nov
2011 |
7 Dec
2011 to 6 June 2012 |
Valid |
|
GW-RS1052-11 |
18 Nov
2011 |
21 Nov
2011 to 18 May 2012 |
Valid |
|
GW-RS1111-11 |
28 Nov
2011 |
29 Nov
2011 to 28 May 2012 |
Valid |
|
GW-RS1116-11 |
28 Nov
2011 |
13 Dec
2011 to 12 June 2012 |
Valid |
|
GW-RS1209-11 |
3 Jan
2012 |
17 Jan
2012 to 16 July 2012 |
Valid |
|
GW-RS0037-12 |
19 Jan
2012 |
1 Feb
2012 to 31 July 2012 |
Valid |
|
GW-RS0051-12 |
19 Jan
2012 |
1 Feb
2012 to 31 July 2012 |
Valid |
|
GW-RS0052-12 |
19 Jan
2012 |
1 Feb
2012 to 30 April 2012 |
Valid |
|
GW-RS0723-11 |
12 Aug 2011 |
15 Aug 2011 to 14 Feb 2012 |
Cancelled |
|
GW-RS0086-12 |
30 Jan 2012 |
3 Feb 2012 to 2 Aug 2012 |
Valid |
|
GW-RS0105-12 |
3 Feb 2012 |
10 Feb 2012 to 9 Aug 2012 |
Valid |
|
GW-RS0153-12 |
17 Feb 2012 |
21 Feb 2012 to 20 Aug 2012 |
Valid |
Discharge
Licence |
WT00006249-2010 |
22 Mar
2010 |
31 Mar
2015 |
Valid |
|
WT00006436-2010 |
15 Apr
2010 |
30 Apr
2015 |
Valid |
|
WT00006673-2010 |
14 May
2010 |
31 Mar
2015 |
Valid |
|
WT00006757-2010 |
28 May
2010 |
31 May
2015 |
Valid |
|
WT00007129-2010 |
28 July
2010 |
31 Jul
2015 |
Valid |
|
WT00008982-2011 |
26 April
2011 |
30 April
2016 |
Valid |
|
WT00009691-2011 |
1 Aug
2011 |
31 July
2016 |
Valid |
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb
2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep
2010 |
N/A |
Valid |
Table 3.7  Summary
of submission status under FEP-01/364/2009
EP Condition |
Submission |
Date of
Submission |
Special Conditions, Clause 2.7 & 2.8 |
Works Schedule and Location Plan |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Environmental Management Organization Chart |
14 Jun 2011 |
Special Conditions, Clause 2.6 |
Commencement Date of Works |
21 Jun 2011 |
Special Conditions, Clause 2.9 |
Noise Management Plan |
28 Jun 2011 |
Condition 2.11 |
Landscape Plan |
23 Aug 2011 |
Condition 2.9 |
Noise Management Plan (Rev.A) |
28-Sep-11 |
Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central
Interchange under FEP-05/364/2009/A
3.1.7.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-05/364/2009A for contract no.
HY/2009/18 are shown in Table
3.8 and Table 3.9.
Table 3.8  Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Permit issued |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0993-11 |
28 Oct 2011 |
28 Oct 2011  br>
25 Apr 2012 |
Valid |
|
GW-RS0132-12 |
08 Feb 2012 |
21 Feb 2012  br>
25 Feb 2012 |
Expired |
Discharge Licence |
WT00008229-2011 |
13 Jan 2011 |
31 Jan 2016 |
Valid |
Registration as a Waste Producer |
WPN: 8335-121-L1048-04 |
17 Dec 2010 |
N/A |
Registration completed |
Billing Account under Waste Disposal
Ordinance (Land) |
Account No.: 7011587 |
11 Oct 2010 |
Account approved |
Valid |
Table 3.9  Summary
of submission status under FEP-05/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 4) |
3 August 2011 |
Contract
no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
3.1.8.
Summary of the
current status on licences and/or permits on environmental protection pertinent
and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.10 and Table 3.11
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov
2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS0749-11 |
11 Aug 2011 |
15 Aug 2011 to 7 Feb 2012 |
Cancelled |
|
GW-RS1021-11 |
4 Nov 2011 |
10 Nov 2011 to 9 May 2012 |
Valid |
|
GW-RS0847-11 |
14 Sep 2011 |
19 Sep 2011 to 16 Mar 2012 |
Cancelled |
|
GW-RS1153-11 |
9 Dec 2011 |
12 Dec 2011 to 16 Mar 2012 |
Cancelled |
|
GW-RS0858-11 |
16 Sep 2011 |
18 Sep 2011 to 16 Mar 2012 |
Cancelled |
|
GW-RS1211-11 |
22 Dec 2011 |
24 Dec 2011 to 21 Jun 2012 |
Valid |
|
GW-RS0883-11 |
4 Oct 2011 |
5 Oct 2011to 4 Apr 2012 |
Valid |
|
GW-RS0820-11 |
5 Sep 2011 |
8 Sep 2011 to 7 Mar 2012 |
Valid |
|
GW-RS1149-11 |
7 Dec 2011 |
8 Dec 2011 to 7 Jun 2012 |
Cancelled |
|
GW-RS1138-11 |
7 Dec 2011 |
8 Dec 2011 to 21 May 2012 |
Valid |
|
GW-RS1190-11 |
30 Dec 2011 |
22 Dec 2011 to 21 Jun 2012 |
Valid |
|
GW-RS0997-11 |
2 Nov 2011 |
2 Nov 2011 to 2 May 2012 |
Valid |
|
GW-RS1021-11 |
4 Nov 2011 |
10 Nov 2011 to 9 May 2012 |
Valid |
|
GW-RS0150-12 |
22 Feb 2012 |
27 Feb 2012 to 24 Aug 2012 |
Valid |
|
GW-RS0094-12 |
1 Feb 2012 |
3 Feb 2012 to 31 Jul 2012 |
Valid |
Registration as a Chemical Waste Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |
Table 3.11 Summary
of submission status under FEP-06/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition
2.6 |
Management
Organization of Main Construction Companies |
11 Mar 2011 |
Amendment
for Management Organization of Main Construction Companies |
16 May 2011 |
|
Condition
2.7 |
Works Schedule |
15 Mar 2011 |
Condition
2.8 |
Location
Plan |
15 Mar 2011 |
Condition
2.23 |
Noise
Management Plan |
6 May 2011 |
Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
3.1.9.
The current status
on licences and/or permits on environmental protection pertinent and submission under
FEP-07/364/2009/A for contract no. HY/2009/19 are shown in Table 3.12 and Table 3.13.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
Notification of Works Under APCO |
326160 |
24
Jan 2011 |
N/A |
Valid |
Registration as a Waste Producer |
7012306 |
10 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste
Producer |
5213-151-C3654-01 |
24 Mar 2011 |
N/A |
Valid |
Application for Vessel Disposal |
7012306 |
21 July 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) |
GW-RS1097-11 |
22-Nov-11 |
07-May-12 |
Cancelled |
|
GW-RS0180-12 |
22-Feb-12 (Effective 27-Feb-12) |
26-Aug-12 |
Valid |
|
GW-RS0028-12 |
18-Jan-12 |
17-Jun-12 |
Valid |
Water Discharge Licence |
WT00010093-2011 |
31-Aug-11 |
30-Sep-16 |
Valid |
|
WT00010865-2011 |
3-Nov-11 |
30-Nov-16 |
Valid |
Table 3.13 Summary
of submission status under FEP-07/364/2009/A
EP Condition |
Submission |
Date of
Submission |
Condition 2.9 |
Noise Management Plan |
02 Jun 2011 |
Condition 2.13 |
Landscape Plan |
7 July
2011 |
Condition 2.9 |
Noise Management Plan(Rev.2) |
28-Oct-11 |
Noise Monitoring Stations
4.1.1.
The noise
monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.
Table
4.1  Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
M7e |
International Finance Centre (Eastern
End of Podium) |
M7w |
International Finance Centre
(Western End of Podium) |
Real time Noise Monitoring Stations
4.1.2.
Review of feasibility on the real time noise monitoring stations was
conducted in July with IEC. Station, RTN1a, Tung Lo Wan fireboat Station was
found not appropriate to be a monitoring station for monitoring the IECL Piling
works and Demolition after visited. 
4.1.3.
The noise
monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the
monitoring works.
Table 4.2  Real
Time Noise
Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.4.
The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing,
statistical results such as L10 and L90 shall also be
obtained for reference.
4.1.5.
Noise monitoring
shall be carried out at all the designated monitoring stations. The monitoring
frequency shall depend on the scale of the construction activities. The
following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
 -
One set of measurements between
0700 and 1900 hours on normal weekdays.
4.1.6.
Real time noise
shall be carried out at the designated monitoring stations. The following is an
initial guide on the regular monitoring frequency for each station on a 24
hours daily basis when noise generating activities are underway:
 -
One set of measurements between
0700 and 1900 hours on normal weekdays.
 -
One set of measurements between
1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public
holidays.
 -
One set of measurements between
2300 and 0700 hours on next day on everyday.
4.1.7.
If construction
works are extended to include works during the hours of 1900  0700 as well as
public holidays and Sundays, additional weekly impact monitoring shall be
carried out during respective restricted hours periods. Applicable permits
under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.8.
As referred to
in the Technical Memorandum  issued under the NCO, sound level meters in
compliance with the International Electrotechnical Commission Publications 651:
1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying
out the noise monitoring. Immediately prior to and following each noise
measurement the accuracy of the sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.9.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
4.1.10. The sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements July be accepted as valid only if the calibration level from
before and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
4.2.1.
The air
monitoring stations for the Project are listed and shown in Table
4.3 and Figure 4.1.. Appendix 4.1 shows the
established Action/Limit Levels for the monitoring works.
Table 4.3  Air
Monitoring Stations
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North Point (Re-commenced on 14
November 2011) |
CMA2a |
Causeway Bay Community Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Garden opposite to
Pedestrian Plaza |
Wan Chai |
MA1e |
International Finance Centre
(Eastern End of Podium) |
Central |
MA1w |
International Finance Centre
(western End of Podium) |
Central |
Remarks:
As per the ENPC meeting in March 2011, the monitoring stations CMA3a  Future
CWB site office at Wanchai Waterfront Promenade was renamed as remark.
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour and
24-hour TSP levels should be measured to indicate the impacts of construction
dust on air quality. The 24-hour TSP levels shall be measured by following the
standard high volume sampling method as set out in the Title 40 of the Code of
Federal Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant
data including temperature, pressure, weather conditions, elapsed-time meter
reading for the start and stop of the sampler, identification and weight of the
filter paper, and any other local atmospheric factors affecting or affected by
site conditions, etc., shall be recorded down in detail.
4.2.4.
For regular
impact monitoring, the sampling frequency of at least once in every six-days,
shall be strictly observed at all the monitoring stations for 24-hour TSP
monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three
times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume
samplers (HVSs) in compliance with the following specifications shall be used
for carrying out the 1-hour and 24-hour TSP monitoring:
 -
0.6  1.7 m3 per minute
adjustable flow range;
 -
Equipped with a timing / control
device with +/- 5 minutes accuracy for 24 hours operation;
 -
Installed with elapsed-time meter
with +/- 2 minutes accuracy for 24 hours operation;
 -
Capable of providing a minimum
exposed area of 406 cm2;
 -
Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
 -
Equipped with a shelter to
protect the filter and sampler;
 -
Incorporated with an electronic
mass flow rate controller or other equivalent devices;
 -
Equipped with a flow recorder for
continuous monitoring;
 -
Provided with a peaked roof
inlet;
 -
Incorporated with a manometer;
 -
Able to hold and seal the filter
paper to the sampler housing at horizontal position;
 -
Easily changeable filter; and
 -
Capable of operating continuously
for a 24-hour period.
4.2.6.
Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7.
A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
4.2.8.
Filter paper of
size 8 x 10 shall be labelled before sampling. It shall be a clean filter
paper with no pinholes, and shall be conditioned in a humidity-controlled
chamber for over 24-hours and be pre-weighed before use for the sampling.
4.2.9.
After sampling,
the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic
bag. The filter paper shall then be returned to the laboratory for
reconditioning in the humidity controlled chamber followed by accurate weighing
by an electronic balance with readout down to 0.1 mg. The balance shall be
regularly calibrated against a traceable standard.
4.2.10. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.2.11. Current calibration certificates of equipments are
presented in Appendix
4.2.
5.0.1.
The
environmental monitoring will be implemented based on the division of works
areas of each designed project managed under different contracts with separate
FEP applied by individual contractors. 
Overall layout showing work areas of various contracts, latest status of
work commencement and monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
In the reporting
month, the concurrent contracts are as follows:
Contract no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
Contract no.
HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced
piling works under FEP-03/364/2009
Contract no.
HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
Contract no.
HY/2009/19  Central  Wanchai Bypass Tunnel (North
Point Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract no.
HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre
Contract no.
HK/2009/02 Wan Chai Development Phase II  Central-Wan Chai Bypass at Wan Chai
East
5.0.3.
The environment
monitoring schedules for reporting month and coming month are presented in Appendix
5.1.
5.1.1.
Monitoring for
report of review baseline noise level was performed from 11 April 2011 to 8
June 2011. Then the report was submitted
on the 20 June 2011, verified by IEC on 18 July 2011 and was approved by ER by
January 2012. The new baseline is used
for the noise calculation of this reporting month starting from January 2012.
Contract no. HY/2009/17 –Central  Wan Chai Bypass (CWB) at FEHD
Whitfield Depot  Advanced piling works under FEP-03/364/2009
5.1.3.5.1.2.
The
proposed division of noise monitoring stations for Contract no. HY/2009/17 are
summarized in Table 5.1 below:
Table 5.1   Noise Monitoring Stations for Contract no.  /span>HY/2009/17
Station |
Description |
M4b |
Victoria
Centre |
5.1.4.5.1.3.
No action
or limit level exceedance was recorded during daytime period in the reporting
month. Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2. 
Contract no. HY/2009/18  Central  Wan Chai
Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
5.1.5.5.1.4.
Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2009/18 are summarized in Table 5.2 below:
Table 5.2
  Noise Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
5.1.6.5.1.5.
No action
and limit level exceedance was recorded during daytime period in the reporting
month Noise monitoring results measured in this
reporting period are reviewed and summarized. 
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2. 
Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under
FEP-02/364/2009 and Contract no. HK/2009/02  Wan Chai Development Phase II  
Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.7.5.1.6.
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011 and HK/2009/02
under FEP-01/364/2009 is on 26 April 2011. The proposed division of noise
monitoring stations are summarized in Table 5.3 below.
Table 5.3
  Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour
Road Sports Centre |
5.1.8.5.1.7.
Noise monitoring results measured in this
reporting period are reviewed and summarized. 
Details of noise monitoring results and graphical presentation can be
referred in Appendix 5.2. Details of the Notification of Exceedance can be referred in Appendix
6.2. 
Contract no. HY/2009/15  Central-Wanchai
Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
5.1.9.5.1.8.
The commencement of construction works for
Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Noise monitoring was commenced on 13 July 2011.
The proposed divisions of noise monitoring stations
are summarized in Table 5.4 below.
Table
5.4   Noise
Monitoring Stations for Contract
no. HY/2009/15
Station |
Description |
M2b |
Noon Gun
Area |
M3a |
Tung Lo
Wan Fire Station |
5.1.10.5.1.9.
No action
or limit level exceedance was recorded in the reporting month. Noise monitoring
results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2
Contract no. HY/2009/19  Central
 Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.1.11.5.1.10.
Noise monitoring for the
tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The
proposed division of noise monitoring stations are summarized in
Table 5.5 below.
Table 5.5
  Noise Monitoring Stations
for Contract
no. HY/2009/19
Station |
Description |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
City
Garden |
M6 |
HK
Baptist Church Henrietta Secondary School |
5.1.12.5.1.11.
No action
or limit level exceedance was recorded in the reporting month. Noise monitoring
results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2
5.2.1.
No construction
activity was conducted during nighttime period (2300 to 0700) in this reporting
month.
Contract no. HY/2009/17 –Central  Wan Chai Bypass (CWB) at FEHD
Whitfield Depot  Advanced piling works under FEP-03/364/2009 and
Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section)
and Island Eastern Corridor Link under FEP-07/364/2009/A
Table 5.6  Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/17
Location
ID |
District |
Description |
RTN1 |
Tin
Hau |
FEHD Hong Kong Transport Section
Whitefield Depot |
Real time noise monitoring results and graphical
presentation during night time period are for information only.
5.2.3.
No action and limit level exceedance were recorded in the reporting
period. Real time noise monitoring results measured in this reporting period
are reviewed and summarized. Details of real time noise monitoring results and
graphical presentation can be referred to Appendix 5.4 .
5.2.4.
The proposed
division of noise monitoring stations are summarized in Table 5.7
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24 April 2011.
Table 5.7  Real Time Noise
Monitoring Stations
for Contract
no. HY/2009/19
Location
ID |
District |
Description |
RTN1 |
Tin
Hau |
FEHD Hong Kong Transport Section
Whitefield Depot |
RTN2 |
North Point |
Oil Street Community Liaison Center |
Real time noise
monitoring results and graphical presentation during night time period are for
information only.
5.2.5.
No action and limit level exceedance were recorded in the reporting
period. Real time noise monitoring results measured in
this reporting period are reviewed and summarized. Details of real time noise
monitoring results and graphical presentation can be referred to Appendix 5.4 .
5.3.1
Due to lack of
electricity supply, the 24-hr TSP monitoring at the following stations were
rescheduled:
CMA1b: from 13 Feb 2012 to 16 Feb 2012
CMA3a: from 13 Feb 2012 to 14 Feb 2012
CMA5a: from 18 Feb 2012 to 20 Feb 2012
Contract no. HY/2009/17 –Central  Wan Chai Bypass (CWB) at FEHD
Whitfield Depot  Advanced piling works under
FEP-03/364/2009
5.3.2
The proposed
division of air monitoring stations are summarized in Table 5.8 below. Air
monitoring for the piling works under contract no. HY/2009/17 was commenced on
8 October 2010.
Table 5.8
  Air
Monitoring Station for Contract no. HY/2009/17
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
Causeway
Bay Community Centre |
5.3.3
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3. 
Contract no. HY/2009/18  Central  Wan Chai
Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
5.3.4
Air monitoring
for the Central Interchange works under contract no. HY/2009/18 was commenced
on 21 April 2011.The proposed division of air monitoring stations are
summarized in Table 5.9 below.
Table 5.9
  Air
Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International
Finance Centre (Eastern End of Podium) |
MA1w |
International
Finance Centre (Western End of Podium) |
5.3.5
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3. 
Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under
FEP-02/364/2009
5.3.6
The commencement
of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality monitoring was commenced on 25 August
2011. The proposed division of air monitoring stations are summarized in Table
5.10 below.
Table 5.10
Air
Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children
Playgrounds opposite to Pedestrian Plaza |
5.3.7
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3. 
Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.3.8
The commencement
of construction works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011.
The proposed division of air monitoring stations are summarized in Table
5.11 below.
Table 5.11
Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society
for the Prevention of Cruelty to Animals |
5.3.9
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3. 
Contract no. HY/2009/15  Central-Wanchai
Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
5.3.10 The commencement of construction works for Contract
no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air quality
monitoring was commenced on 14 July 2011. The proposed division of air monitoring stations are
summarized in Table 5.12 below.
Table
5.12 Air Monitoring Station for Contract
no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE
Site Office |
5.3.11
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3. 
Contract no. HY/2009/19  Central
 Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor
Link under FEP-07/364/2009/A
5.3.12
The proposed
division of air monitoring stations are summarized in Table 5.13 below. Air
monitoring for the tunnel works under contract no. HY/2009/19 was commenced on
26 April 2011.
Table 5.13
Air Monitoring
Stations
for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil St
Community Liaison Centre |
CMA2a |
Causeway
Bay Community Centre |
5.3.13
No exceedance
was recorded in the reporting month. Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/17 –Central  Wan Chai
Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009
5.4.1.
No Inert and
non-inert C&D wastes were disposed in the reporting month. Details of the
waste flow table are summarized in Table 5.14
Table 5.14 Details
of Waste Disposal for Contract no. HY/2009/17
Waste Type |
Quantity
this month, m3 |
Cumulative
Quantity-to-Date, m3 |
Disposal
/ Dumping Grounds |
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert
C&D materials recycled |
N/A |
||
Non-inert
C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
N/A |
N/A |
N/A |
Contract nos.
HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009
5.4.2.
Inert and
non-inert C&D wastes were disposed of in this reporting month. Details of
the waste flow table are summarized in Table 5.15.
Table 5.15 Details
of Waste Disposal for Contract no. HK/2009/01
Waste
Type |
Quantity this month, m3 |
Cumulative-to-Date, m3 |
Disposal / Dumping Grounds |
Inert
C&D materials disposed |
2447.87 |
16540.09 |
TKO137, TM38 |
Inert
C&D materials recycled |
0 |
389.96 |
N/A |
Non-inert
C&D materials disposed |
46.34 |
609.96 |
SENT Landfill |
Non-inert
C&D materials recycled |
0 |
135754 |
N/A |
Chemical
waste disposed |
150 |
5660 |
N/A |
Contract no.
HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
5.4.3.
Inert C&D &
non-inert C&D wastes were disposed of in this reporting month. Details of
the waste flow table are summarized in Table 5.16.
Table
5.16 Details of Waste Disposal for Contract no.
HK/2009/02
Inert
C&D materials disposed |
13,567 |
87,749 |
TKO137, TM 38 |
Inert
C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed |
35 |
181 |
SENT Landfill |
Non-inert
C&D materials recycled |
NIL |
NIL |
N/A |
Chemical
waste disposed |
1,400 |
3,175 |
N/A |
Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central
Interchange under FEP-05/364/2009/A
5.4.4.
Inert C&D
and non-inert C&D waste was disposed of in this reporting month. Details of
the waste flow table are summarized in Table 5.17.
Table 5.17 Details
of Waste Disposal for Contract no. HY/2009/18
Inert
C&D materials disposed |
2347 |
15199.1 |
T.K.O. 137 |
Inert
C&D materials recycled |
N/A |
||
Non-inert
C&D materials disposed |
9.2 |
219.8 |
SENT Landfill |
Non-inert
C&D materials recycled |
N/A |
||
Chemical
waste disposed |
N/A |
Contract no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
5.4.5.
Inert & Non-inert C&D wastes were
disposed of in this reporting month. Details
of the waste flow table are summarized in Table 5.18.
Table 5.18 Details of Waste Disposal
for Contract no. HY/2009/15
Inert
C&D materials disposed |
44205.6 |
118145.2 |
Tuen Mun Area 38 |
|
19.3 |
892.5 |
TKO137 FB |
Inert
C&D materials recycled |
NIL |
413 |
HY/2009/11 ex-PCWA TS4 |
Non-inert
C&D materials disposed |
23.5 |
124.2 |
SENT Landfill |
Non-inert
C&D materials recycled |
NIL |
340 |
Xun
Xiang Metalware Skylight
Recycle (paper) |
Chemical
waste disposed |
NIL |
8000 |
Dunwell Group |
Contract
no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
5.4.6.
Inert and
Non-inert C&D wastes were disposed of in this reporting month. Details of
the waste flow table are summarized in Table 5.19.
Table 5.20 Details
of Waste Disposal for Contract no. HY/2009/19
Inert
C&D materials disposed |
11760.02 |
21885.29 |
N/A |
Inert
C&D materials recycled |
NIL |
630.954 |
N/A |
Non-inert
C&D materials disposed |
53.58 |
89.661 |
SENT Landfill |
Non-inert
C&D materials recycled |
13.25 |
13.43 |
N/A |
Chemical
waste disposed |
1.68 |
1.78 |
N/A |
6.0.1.
The Event Action
Plan for construction noise, air qualities are presented in Appendix 6.1.
Contract no. HY/2009/17 –Central
 Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009
6.1.1.
No exceednace was recorded in the reporting month.
Contract
no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
6.1.2.
No exceednace was recorded in the reporting month.
Contract no. HK/2009/01  Wan Chai Development Phase II
 Central  Wan Chai Bypass at Hong Kong Convention Exhibition Centre  Tunnel
Works under FEP-02/364/2009
6.1.3.
No exceednace was recorded in the reporting month.
Contract
no. HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.4.
No exceednace was recorded in the reporting month.
Contract no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
6.1.5.
No exceednace was recorded in the reporting month.
Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.6.
No exceednace was recorded in the reporting month.
Real Time Noise Monitoring
Contract no. HY/2009/17  
Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009
6.1.7.
No exceednace was recorded in the reporting month.
Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.8.
No exceednace was recorded in the reporting month.
Contract
no. HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  
Advanced piling works under FEP-03/364/2009
6.2.1.
No exceedance was recorded in the reporting month.
Contract
no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
6.2.2.
No exceednace was recorded in the reporting month.
Contract
no. HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009
6.2.3.
No exceednace was recorded in the reporting month.
Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.2.4.
No exceednace was recorded in the reporting month.
Contract no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay
Typhoon Shelter Section) FEP-06/364/2009/A
6.2.5.
No exceednace was recorded in the reporting month.
Contract
no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
6.2.1
No exceednace was recorded in the reporting month.
6.3.1.
There was no
non-compliance from the site audits in the reporting period. The observations
and recommendations made in each individual site audit session were presented
in Section 8.
6.3.2.
No
project-related non-compliance from monitoring was recorded in the reporting
month.
7.0.1.
According to
Condition 3.4 of the EP-364/2009/A, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern
Corridor Link projects (IECL) and Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai
East (CWB Tunnel).
7.0.2.
Monthly EM&A report (January 2012) of Central
Reclamation Phase III (CRIII) is outstanding in this reporting period, no cumulative
construction impact due to the concurrent activities of the current projects with
the Central Reclamation Phase III (CRIII) could be done.
7.0.3.
According to the construction programme of Central Reclamation
Phase III, Wan Chai Development Phase II, Central-Wan Chai Bypass
and Island Eastern Corridor Link projects, the major construction activity
under Central
Reclamation Phase III were general filling works in IRAE; Wan Chai
Development Phase II was marine works at HKCEC areas, cross-harbour Watermains,
Fresh Watermains, Cooling Watermains and Salt Watermains Installations, tunnel
works at Wan Chai East, seawall block construction, reclamation work and
diaphragm wall construction at TS4; Diaphragm wall construction at TS1 and
TPCWAE TCBR1W. Advanced piling works at FEHD Whitfield Depot, Central
Interchange, and diaphragm wall construction at North Point area. The major
environmental impact was water quality impact at Causeway Bay and Wan Chai.
Land-based construction activity were advance filling works at TS4, Diaphragm
wall construction at TS1 and TPCWAE TCBR1W, piling works at FEHD
Whitfield Depot, Diaphragm wall at Central and North Point and tunnel works at
Wan Chai East in the reporting month.
7.0.4.
The major environmental impacts generated from CRIII advanced
piling works at FEHD Whitfield Depot were undertaken and Diaphragm wall
construction at Central and tunnel works at Wan Chai East, IECL and Causeway
Bay typhoon shelter in the reporting month. No significant air, noise impact
were anticipated in the reporting month. Besides, no Project-related exceedance
was recorded during the environmental monitoring events in the reporting month. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Wan Chai Development
Phase II and Central Reclamation Phase III was
insignificant.
8.0.1.
During this
reporting month, weekly environmental site audits were conducted for Contracts
no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01 and HK/2009/02.
No non-conformance was identified during the site audits.
8.0.2.
Four site
inspections for Contract no. HY/2009/15 was carried out during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.1.
Table 8.1  Summary
of Environmental Inspections for Contract no. HY/2009/15
Date |
Item |
Observations |
Action taken by Contractor |
Outcome |
31-Jan-12 |
120131_01 |
The silt
curtains for southern and eastern seawall
protection at TS4 should be improved. |
Improvement of silt curtains /ins> |
Completion
as observed on 7-Feb-12 |
31-Jan-12 |
120131_02 |
Maintenance
shall be provided for the oil leaking plant. Also, this plant shout be
suspended before repaired. (TS1) |
|
Completion
as observed on 7-Feb-12 |
31-Jan-12 |
120131_03 |
Wastewater
should be treated properly prior discharge. (ExTCPWA) |
Collect and treat the |
Completion
as observed on 7-Feb-12 |
7-Feb-12 |
120207_01 |
Mud trail
should be tidied up. (TS4). |
Tidy up mud trail. |
Completion
as observed on 14-Feb-12 |
7-Feb-12 |
120201_02 |
Oil
spillage resulted from the oil filling activity should be treated (TS1). |
Clear up oil spillage. |
Completion
as observed on 14-Feb-12 |
14-Feb-12 |
120214_01 |
Eastern
slopping seawall was found dislocated. The contractor should rectify it A.S.A.P. (TS4) |
|
Completion
as observed on 21-Feb-12 |
14-Feb-12 |
120214_02 |
Wastewater
from drilling work should be treated properly prior discharge. (TS4) |
Treatment of wastewater prior discharge. |
Completion
as observed on 21-Feb-12 |
21-Feb-12 |
120221_01 |
The damaged Chemical |
Replacement of damaged cabinet |
Completion
as observed on 28-Feb-12 |
8.0.3.
Four site
inspections for Contract no. HY/2009/18 was carried out during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.2.
Table 8.2  Summary
of Environmental Inspections for Contract no. HY/2009/18
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
120202_01 |
2-Feb-12 |
A drip
tray was filled by mud. The contractor was reminded to collect |
collect the stagnate mud in the drip tray |
Completion
as observed on 9-Feb-12 |
120209_01 |
9-Feb-12 |
Improve
maintenance of noise barrier to ensure no gap is present. |
Improve
maintenance of noise barrier |
Completion
as observed on 16-Feb-12 |
120223_01 |
23-Feb-12 |
Make
sure proper size drip tray is used for oil drums (at new Man Yiu Street) |
Change
drip tray for oil drums to appropriate size. |
Completion
as observed on 1-Mar-12 |
8.0.4.
Four site
inspections for Contract no. HY/2009/19 was
carried out during this reporting period. The results of these inspections and outcomes are summarized in Table
8.3.
Table 8.3  Summary
of Environmental Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
120201_01 |
1-Feb-12 |
Protection
zone of tree (914) shall be enlarged. |
Enlarge
tree protection zone. |
Completion
as observed on 22-Feb-12 |
120201_02 |
1-Feb-12 |
Oil shall be collected from drip trip at
regular intervals to prevent leakage. (Work stationF5) |
Collection of oil from drip trips at regular intervals. |
Completion
as observed on 8-Feb-12 |
120208_01 |
8-Feb-12 |
Improve
and maintain silt
curtain to ensure no gaps are between curtains at work platform 7&8. |
Improve
and maintain silt
curtain |
Completion
as observed on 15-Feb-12 |
120215_01 |
15-Feb-12 |
Tidy up muddy trail to ensure no mud is generated out of site area. (Oil street exit) |
Tidy up
muddy trail |
Completion
as observed on 22-Feb-12 |
120215_02 |
15-Feb-12 |
U-channel
should be cleared at regular intervals to ensure no runoff get off site.
(Near Oil street exit) |
Clear
mud in u-channel at regular intervals. |
Completion
as observed on 22-Feb-12 |
120222_01 |
22-Feb-12 |
Ensure U-channel is clear of
blockage and no runoff to outside site area. (near Oil Street) |
Clear
rubbish inside u-channel. |
Completion
as observed on 29-Feb-12 |
120222_02 |
22-Feb-12 |
Silt curtain should be well
maintained to ensure no gaps and silt curtains are not floating. (Station 4) |
Maintenance of silt curtain |
Completion
as observed on 29-Feb-12 |
120222_03 |
22-Feb-12 |
Ensure no mud trail at exit. (Oil Street). |
Ensure all vehicles leaving site area have
completed wheel-wash process. |
Completion
as observed on 29-Feb-12 |
8.0.5.
Four site inspections for Contract no. HK/2009/01 was
carried out during this reporting period. The results of these inspections and
outcomes are summarized in Table 8.4.
Table 8.4  Summary of Environmental
Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
120201_01 |
1-Feb-12 |
The
design of the vehicle wheel-washing bay northbound of HKCEC to avoid any
wastewater spillage out of site boundary. |
Improve design of the vehicle wheel washing bay |
Completion
as observed on 8-Feb-12 |
120208_01 |
8-Feb-12 |
Proper
shelter/cover should be provided over 20 nos. bagged cement bags at HKCEC water
channel and grouting plant near Grand Hyatt. |
Proper
shelter/cover for over 20 nos. bagged cement bags and grouting plant |
Completion
as observed on 15-Feb-12 |
120208_02 |
8-Feb-12 |
Oil drum
on unpaved land (HKCEC water channel) should be removed. |
Remove oil drum from unpaved land |
Completion
as observed on 15-Feb-12 |
120215_01 |
15-Feb-12 |
Contractor
was reminded to avoid storage of the C&D material too close to
the sheet-pile wall at HKCEC water channel. |
Avoid storage of C&D material close to sheet-pile wall |
Completion
as observed on 22-Feb-12 |
120224_01 |
24-Feb-12 |
The barrier should be surrounded
to the stockpile storage adjacent to VIP drop off area. |
Provide barrier to stockpile storage. |
The next inspection was not in the reporting month and cannot provide
observations. |
8.0.6.
Four site
inspections for Contract no. HK/2009/02 was carried out during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.5.
Table 8.5   Summary
of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
120202_01 |
2-Feb-12 |
Sediment
inside the sedimentation tank should be regular removed. |
Regular removal of sediment inside sedimentation tank. |
Completion
as observed on 10-Feb-12 |
120210_01 |
10-Feb-12 |
Chemical
containers should be place on the drip tray. (ex-Pet Garden) |
Place chemical containers on drip tray. |
Completion
as observed on 16-Feb-12 |
120210_02 |
10-Feb-12 |
Oil stain
found on the
drip tray should be removed properly. |
Removal of oil stain on drip tray. |
Completion
as observed on 16-Feb-12 |
120216_01 |
16-Feb-12 |
Improve
design on u-channel (sump pit) to ensure water is clear when entering
drainage. |
Improve
design on u-channel (sump pit). |
Completion
as observed on 22-Feb-12 |
120216_02 |
16-Feb-12 |
Enlarge
shelter for covering grouting area. |
Enlarge
shelter over grouting area. |
Completion
as observed on 22-Feb-12 |
120222_01 |
22-Feb-12 |
Dark smoke emission from flat top
barge and tug boat (no. B2934) was
observed. Maintenance work should be provided to these vessels. |
Maintenance
of vessels within site area. |
Completion
as observed on 1-Mar-12 |
120222_02 |
22-Feb-12 |
Water mixed with bentonite located closed to the roadside at Wan Shing Street should be removed. |
Removal
of bentonite from roadside. |
Completion
as observed on 1-Mar-12 |
8.0.7.
Four site
inspections for Contract no. HY/2009/17 were carried out during this reporting
period. No observation was found in the reporting month.
9.0.1.
No environmental complaint was received in this
reporting month.
9.0.2.
The details of cumulative complaint
log and updated summary of complaints are presented in Appendix
9.1
9.0.3.
Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1  Cumulative
Statistics on Complaints
Reporting
Period |
No. of
Complaints |
Feb 12 |
0 |
Sep 10 to Jan 12 |
17 |
Total |
17 |
Table 9.2  Cumulative Statistics on Successful Prosecutions
Environmental
Parameters |
Cumulative
No. Brought Forward |
No. of
Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2. The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table 10.1   Summary of Key Construction Activities of Individual
Contract(s) to be commenced in Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation
Measures |
HY/2009/15 |
 -
Diaphragm wall construction at TS4  -
ELS works at TS1 and TPCWAE  -
Night time protection works at CHT  -
Cut off wall preparation works at Hung Hing Road and POC |
 -
Watering any dust generating activities  -
Checking all drip trays frequently and clear any stagnant water and
mud inside it.  -
Noise control measures shall be provided during restricted hours. |
HY/2009/17 |
 -
ELS works for basement construction for pile cap construction. |
 -
Noise
barrier shall be implemented; and  -
Watering
any dust generating activities |
HY/2009/18 |
 -
Instrumentation works for Manholes and Intake Culvert Survey  -
Excavation of trial pit  -
Drainage work  -
Site investigation and pre-drilling works  -
Diaphragm wall construction  -
Hoarding erection  -
Roadwork  -
Grout curtain  -
Sheet-piling  -
Tree pruning |
 -
Noise barrier shall be implemented; and  -
Noise level shall be controlled by reducing piling rate and no. of
plants working in parallel.  -
Dust control during dust generating works |
HY2009/19 |
 -
Road
works at Watson Road  -
Fabrication
of bored piling platform  -
Bored
piling (Land)  -
Ground
contamination assessment  -
Pre-drilling
works for bored pile and Diaphragm wall  -
D-wall
Construction (North & South Section)  -
Guide
wall construction for D-wall / Barette at North side  -
Construction
works for Box Culvert T  -
Marine
Piling  -
Installation
of temporary steel bridge at Culvert U |
 -
Noise
level shall be controlled by reducing the pilling operation rate. |
HK2009/01 |
 -
Diaphragm
wall construction works for both CWB and SCL Protection Works  -
Guide
wall for construction of CWB Diaphragm wall at Stage 2  -
Pilling
works for CWB and exhaust duct at Stage 1  -
Pilling
works for SCL Protection Works  -
Installation
of sheet pile for construction of exhaust duct  -
Excavation
woks  -
Installation
of sheet pile for construction exhaust duct  -
Installation
of sheet pile for construction of SCL top slab |
 -
Noise
level shall be controlled by reducing pilling rate and no. of plants working
in parallel.  -
Well
maintain the enclosures for grouting and bentonite mixing plants. |
HK/2009/02 |
 -
Deep
excavation works below -0.9mPD for western tunnel portion and below +1.5mPD
for eastern tunnel portion.  -
Shear
pin and Pumping test at WCR1 area. |
 -
Noise
level shall be controlled by reducing pilling rate.  -
Well
maintain the enclosures for grouting and bentonite mixing plants. |
10.0.3. The construction works of Contract no. 04/HY/2006  
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
was completed, and the FEP was surrendered by the Contractor on 11 February
2011.